Kesselaiu elektrivarustuse 2.etapi ehitustööd
Published and bidding deadline .
Integrity Indicators
2 out of 4- Has a single bidder
- No disputes from bidders or outsiders
- Sellers have not recently made any political party donations
- Bidding period is associated with an increased risk factor
Estimated Cost
€0Actual Cost
Duration
2 daysBidders
1 bidderBids
1 bidDisputes
0 disputesProcess Type | Väljakuulutamiseta läbirääkimistega hankemenetlus |
---|---|
Offers Revealed At |
Contracts
OÜ Energogen1. Ehituse töövõtuleping Signed with completion deadline . | €83,613.30 est. €83,613.30 |