Integrity Indicators

3 out of 4
  • Has multiple bidders
  • No disputes from bidders or outsiders
  • Sellers have not recently made any political party donations
  • Bidding period is associated with an increased risk factor

Estimated Cost

 

Actual Cost

 

Duration

27 days

Bidders

10 bidders

Bids

10 bids

Disputes

0 disputes
Process TypeOpen procedure
Offers Revealed At
Showing board-level people associated with the buyer and seller organizations 12 months prior up to 12 months after the procurement process. Also shown are their political affiliations and donations within the same period.

Contracts

EstoniaEmpower Aktsiaselts

1. RAAMLEPING RIA-Empower

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaCorle OÜ

10. RAAMLEPING RIA-Corle

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaLansec Tele OÜ

2. RAAMLEPING RIA-Lansec

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaLansec Tele OÜ

2-12. tellimus Optilise kaabli paigaldamine Pärnu 12, Sindi 213281

Signed .

€11,155
est. €11,155

EstoniaLansec Tele OÜ

2-12. tellimus Optilise kaabli paigaldamine Pärnu 12, Sindi 213281

Signed .

€11,155
est. €11,155

EstoniaAktsiaselts Haberst Infra

3. RAAMLEPING RIA-Haberst

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaFiberup OÜ

4. RAAMLEPING RIA-Fiberup

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaINSTWORK OÜ

5. RAAMLEPING RIA-Instwork

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaINSTWORK OÜ

5-4. Üleandmise-vastuvõtmise akt Saku Tallinna mnt 12

Signed .

€4,300
est. €4,300

EstoniaMTR Halduse OÜ

6. RAAMLEPING RIA-MTR Haldus

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaAKTSIASELTS TELEGRUPP

7. RAAMLEPING RIA-Telegrupp

Signed with completion deadline .

€5.55M
est. €5.55M

EstoniaAKTSIASELTS TELEGRUPP

7-1. Tellimus , TG pakkumus 09/01/2019

Signed .

€15,877.70
est. €15,877.70

EstoniaAS Connecto Eesti

8. RAAMLEPING RIA-Connecto

Signed with completion deadline .

€5.55M
est. €5.55M

Estoniaosaühing Rewire

9. RAAMLEPING RIA-Rewire

Signed with completion deadline .

€5.55M
est. €5.55M