Mustvee-Kasepää kergliiklustee projekteerimis-ehitustööde teostamine
Published and bidding deadline .
Integrity Indicators
3 out of 4- Has multiple bidders
- No disputes from bidders or outsiders
- Sellers have not recently made any political party donations
- Bidding period is associated with an increased risk factor
Estimated Cost
Actual Cost
€633,304Duration
26 daysBidders
5 biddersBids
4 bidsDisputes
0 disputesProcess Type | Open procedure |
---|---|
Offers Revealed At |
Contracts
Verston Ehitus OÜ1. Töövõtuleping Signed with completion deadline . | €633,304 est. €633,304 |