Nõmme Gümnaasiumi spordihoone (Põllu tn 68) projekteerimine
Published and bidding deadline .
Integrity Indicators
5 out of 5- Has multiple bidders
- Estimated and actual costs are within range
- No disputes from bidders or outsiders
- Sellers have not recently made any political party donations
- Bidding period is adequate
Estimated Cost
€225,000Actual Cost
€189,450Duration
40 daysBidders
7 biddersBids
6 bidsDisputes
0 disputesProcess Type | Open procedure |
---|---|
Offers Revealed At |
Contracts
AS Infragate Eesti1. Töövõtuleping Signed with completion deadline . | €189,450 est. €189,450 |