Integrity Indicators

4 out of 5
  • Has multiple bidders
  • Estimated and actual costs are within range
  • No disputes from bidders or outsiders
  • Sellers have not recently made any political party donations
  • Bidding period is associated with an increased risk factor

Estimated Cost

€9.10M

Actual Cost

€7.74M

Duration

56 days

Bidders

11 bidders

Bids

8 bids

Disputes

0 disputes
Process TypeOpen procedure
Offers Revealed At
Showing board-level people associated with the buyer and seller organizations 12 months prior up to 12 months after the procurement process. Also shown are their political affiliations and donations within the same period.

Contracts

EstoniaOÜ Nordlin Ehitus

1. Töövõtuleping

Signed with completion deadline .

€7.74M
est. €7.74M