Rapla kunstmurustaadioni ja infrastruktuuri ehitustööd
Published and bidding deadline .
Integrity Indicators
2 out of 5- Has a single bidder
- Actual cost beyond the estimated cost
- No disputes from bidders or outsiders
- Sellers have not recently made any political party donations
- Bidding period is associated with an increased risk factor
Estimated Cost
€0Actual Cost
€879,057Duration
7 daysBidders
1 bidderBids
1 bidDisputes
0 disputesProcess Type | Minikonkurss raamlepingu alusel |
---|---|
Offers Revealed At |
Contracts
OÜ Kivipartner1-1. Hankeleping nr 12-12/260-1 Signed . | €879,057 est. €879,057 |