Kontaktvõrgu ümberehituse projekteerimine
Published and bidding deadline .
Integrity Indicators
3 out of 4- Has multiple bidders
- No disputes from bidders or outsiders
- Sellers have not recently made any political party donations
- Bidding period is associated with an increased risk factor
Estimated Cost
Actual Cost
€51,600Duration
28 daysBidders
2 biddersBids
1 bidDisputes
0 disputesProcess Type | Lihthange |
---|---|
Offers Revealed At |
Contracts
GRK Rail Oy1. Leping 14764 Signed with completion deadline . | €51,600 est. €51,600 |